STUDY TEAM

Misha Golfman, MRP, team leader

Mac Rood, MRP Board Chair

Jennifer Conley, Director of Transportation Systems, VHB, Consultant

Joshua Schwartz, MRVPD Executive Director

Reuben McMartin, CVRPC, Senior Transportation Planner, MPM

Scott Robertson, VTrans Coordinator

study timeline

Task Timeline
Project Kick-off Meeting September 2024
Compile Base Mapping / Document Existing Conditions September – November 2024
Identify Resource Constraints & Permitting Requirements October – December 2024
Public Meeting #1 – Local Concerns Meeting Late November 2024 (week of 11th or 18th)
Develop Conceptual Alternatives December 2024 – March 2025
Public Meeting #2 – Alternatives Presentation Mid March 2025
Draft Scoping Study Production March to May 2025
VTrans Review (minimum 3 weeks plus 2 weeks for comment resolution) May to June 2025
Public Meeting #3 – Presentation of Draft Ranked Alternatives June 2025
Final Scoping Study Production & Submission July 2025