STUDY TEAM
Misha Golfman, MRP, team leader
Mac Rood, MRP Board Chair
Jennifer Conley, Director of Transportation Systems, VHB, Consultant
Joshua Schwartz, MRVPD Executive Director
Reuben McMartin, CVRPC, Senior Transportation Planner, MPM
Scott Robertson, VTrans Coordinator
study timeline
Task | Timeline |
---|---|
Project Kick-off Meeting | September 2024 |
Compile Base Mapping / Document Existing Conditions | September – November 2024 |
Identify Resource Constraints & Permitting Requirements | October – December 2024 |
Public Meeting #1 – Local Concerns Meeting | Late November 2024 (week of 11th or 18th) |
Develop Conceptual Alternatives | December 2024 – March 2025 |
Public Meeting #2 – Alternatives Presentation | Mid March 2025 |
Draft Scoping Study Production | March to May 2025 |
VTrans Review (minimum 3 weeks plus 2 weeks for comment resolution) | May to June 2025 |
Public Meeting #3 – Presentation of Draft Ranked Alternatives | June 2025 |
Final Scoping Study Production & Submission | July 2025 |